Construction disputes over payments, delays or defects need quick resolution. Adjudication delivers this through a statutory process that typically concludes within 28 days.
The adjudicator’s decision is binding and must be complied with immediately. However, there are limited circumstances where it can be challenged.
Adjudication Under the 1996 Act
The Housing Grants, Construction and Regeneration Act 1996 (as amended in 2009) gives parties in most construction contracts the right to refer disputes to adjudication at any time. The process is designed to provide a rapid interim decision to maintain cash flow and keep projects moving.
Common disputes referred to adjudication include:
The adjudicator’s decision is binding until the dispute is finally determined by litigation or arbitration.
Binding But Not Final
An adjudication decision must be complied with immediately, even if a party disagrees with it. This is often described as “pay now, argue later.” The purpose is to prevent disputes from stopping work or causing cash flow problems on projects.
However, the decision is not final. Either party can refer the underlying dispute to court proceedings or arbitration for a full rehearing. At that stage, the entire matter is considered afresh. The court or arbitrator is not bound by the adjudicator’s findings.
In practice, most parties accept the adjudication decision and do not pursue further proceedings. The cost and time involved in litigation or arbitration means that adjudication effectively resolves many disputes.
Grounds to Resist Enforcement
If a party fails to comply with an adjudication decision, the other party can bring enforcement proceedings in the Technology and Construction Court (TCC). These proceedings are dealt with quickly, often within weeks.
The courts adopt a strongly pro-enforcement approach. Even where the adjudicator has made clear errors of fact or law, the decision will usually be enforced. The policy is to uphold the interim nature of adjudication and preserve its effectiveness as a dispute resolution mechanism.
There are only limited grounds on which enforcement can be resisted:
Lack of Jurisdiction
The adjudicator must have had jurisdiction to decide the dispute. Jurisdiction challenges typically involve:
Breach of Natural Justice
The adjudicator must give both parties a fair opportunity to present their case. A breach of natural justice may arise if:
Material Breach of the Rules
Adjudicators must follow the procedural rules set out in the contract or the Scheme for Construction Contracts. Serious breaches may prevent enforcement, though minor procedural irregularities will not.
The threshold for successfully resisting enforcement is high. The courts will not interfere unless there is a serious procedural failing that goes to the heart of the adjudicator’s jurisdiction or the fairness of the process.
Severable Decisions
Where only part of an adjudicator’s decision is flawed, the court may enforce the valid parts and set aside the defective element. This depends on whether the decision can be properly severed without undermining the adjudicator’s overall reasoning.
Correcting Errors in Decisions
Once an adjudicator has issued their decision, they cannot reopen it or reconsider their findings. The only exception is for clerical or typographical errors, which can be corrected within a short period (typically five days or less).
An adjudicator cannot:
If there are substantive errors in the decision, the only remedy is to refer the dispute to court or arbitration for final determination.
Referring Disputes to Court or Arbitration
A party dissatisfied with an adjudication decision can commence court proceedings or arbitration (if the contract provides for it) to have the dispute determined finally. The entire dispute is reconsidered without any deference to the adjudicator’s findings.
This route involves significant cost and time. Proceedings in the TCC or arbitration can take many months or even years to reach a final hearing. Legal costs often run into six figures for substantial construction disputes.
For this reason, most parties do not pursue final determination after adjudication. The adjudication decision effectively becomes the final resolution of the dispute.
Time Limits for Enforcement
There is no statutory time limit for bringing enforcement proceedings. However, the court may refuse to enforce a decision if there has been unreasonable delay, particularly if circumstances have changed in the meantime or the delay has prejudiced the other party.
Parties seeking to enforce an adjudication decision should act promptly.
Withholding Payment Pending Challenge
A party cannot withhold payment whilst challenging an adjudication decision. Compliance is required immediately, even if enforcement proceedings have been issued to resist the decision.
Failure to comply will usually result in summary judgment being granted in the enforcement proceedings.
Frequently Asked Questions
Alternative Approaches
Where adjudication is not appropriate or the decision is unsatisfactory, parties may consider:
Each of these options has different costs, timescales and procedural requirements. The most appropriate route depends on the nature of the dispute and the parties’ objectives.
Getting Legal Advice
Construction adjudication moves quickly. If you are considering referring a dispute to adjudication, or if adjudication proceedings have been commenced against you, early legal advice is important.
Our commercial litigation team has experience advising on construction disputes and adjudication proceedings. We can help you understand your position, prepare your case, and advise on enforcement or challenge where appropriate.
Contact us on 01604 344562 (Northampton) or 01908 916096 (Milton Keynes), or email [email protected].
Disclaimer: The information provided on this blog is for general informational purposes only and is accurate as of the date of publication. It should not be construed as legal advice. Laws and regulations may change and the content may not reflect the most current legal developments. We recommend consulting with a qualified solicitor for specific legal guidance tailored to your situation.

Written by George Smith
Head of Litigation and Dispute Resolution, Dispute Resolution at Franklins Solicitors LLP
Specialises in contentious trusts and probate, landlord and tenant matters, debt recovery, contract disputes, Court of Protection, lease extensions, injunctions, guarantor advice and boundary disputes.
George Smith is a Chartered Legal Executive and Commissioner of Oaths with over 29 years’ experience in civil and commercial litigation and dispute resolution. He originally joined Franklins Solicitors in 1994, rejoining in 2023 after a 20-year break.
George handles a broad range of matters including contentious trusts and probate, landlord and tenant disputes, debt recovery, defamation, contract disputes and Court of Protection issues. Known for his no-nonsense, calm approach, he focuses on delivering swift and effective solutions to complex disputes.
Outside work, George enjoys backgammon, reading books, attending concerts, travelling and sharing his passion for the 1980s with his four children.



